Mark a chalk line to identify the end of your first layer.
How to install roll roofing shingles.
Install roll roofing measure 35 inches up from the eaves at several intervals along the roof and mark them.
To seal a plumbing vent spread roofing.
Apply roofing cement to the roof.
Install roll roofing when the temperature is at least 50 degrees fahrenheit to keep the material from cracking.
Repeat this on both sides of the roof.
Prepare a valley between joined roofs by cutting a strip that is 18 inches wide and covers the entire length of the valley.
Drip edge or drip cap is either plastic or sheet metal.
Plan so that no two butt joints are closer than 2 feet from each other.
Use the chalk line to snap a straight line vertically every 6 inches.
Snap a chalk line as a guide for the first layer roofing.
Install peel and stick roofing in a similar manner.
Do not use the eaves as a guide instead because they can be uneven.
For extra durability you may install roll roofing in two layers.
It not only protects the roof but it also protects the fascia.
How to do it attach first course.
Use a trowel to scoop up the roofing cement.
Spread the roofing cement along the.
Nail it in place with roofing nails that penetrate at least 3 4 inch into.
Using a measuring tape measure 35 inches 89 cm up from.
Every 5 inches make a new mark until you get to the rop of the roof.
Position the first course so it overhangs the drip edges by about 1 4 inch and roll it out a.
Installing the rolled roofing 1.
The strips should always be horizontal.
Cut the rolled roofing.